Flood protection Ostrach

    Solution ID
    Description of solution
    Summary (Challenges; Objectives)

    In the course of the extension of the flood protection, the Ostrach was also expanded and ugraded ecologically. The river bed was widened, as far as the existing local utilization conditions allowed it. All exisiting drop structures were replaced with river bed ramps to improve the ecological passability. Groynes and large stones were implemented to improve the flow diversity. 

    Technical characteristics

    2 km river widening

    Location Latitude
    47.5176000000
    Location Longitude
    10.2908000000
    Comment on location

    Sonthofen

    Keywords
    Ecosystem (s) impacted
    Riverfront
    Hazard(s) concerned
    Floods
    Other challenges
    Biodiversity
    Exposition
    Exposed assets
    Urban settings
    Is there population exposed?
    Yes, high density of population (>200 persons/km2)
    Activity
    Are there jobs created in the nature-based sector?
    Don't know
    Are there new employments in tourism sector, sport activities or recreational activites ?
    Don't know
    Are there new activities in the tourism sector , sport activities or recreational activites?
    Don't know
    Are there new/traditional activities that increased?
    Others
    International classification
    Sustainable development goals addressed
    SDG 13 – Climate action
    Sendai Frameword priorities addressed
    Priority 3. Investing in disaster risk reduction for resilience
    Actors
    Who are the beneficiaries of the action
    inhabitants of Sonthofen
    Organizations involved in the implementation of the action

    water authority Kempten, Planning community Hochwasserschutz Ostrach (consisting of Regierungsbaumeister Schlegel GmbH & Co. KG, Schneider & Theisen GmbH Ingenieurbüro für Bauwesen, Arnold Consult AG and aquasoli Ingenieurbüro), Dr. Ebel & Co. Ingenieurgesellschacft für Geotechnik und Wasserwirtschaft mbH, Ingenieur- und Sachverständigenbüro für Bauwesen Dipl.-Ing. (FH) Peter Ungethüm GmbH, LGA Landesgewerbeanstalt Bayern and Dipl. Ing. Norbert Nieder, Monika und Armin Socher SigeKo GbR, Hubert Schmid Bauuntrnehmen GmbH, Geiger Hoch- und Tiefbau GmbH & Co. KG, Dobler GmbH & Co. KG, Brutscher GmbH & Co. KG, IBS Technics GmbH, Siegfried Kiffer GmbH

    Temporal aspects
    Design life time of the action
    More than 10 years
    Implementation time of the action
    Between 5 and 10 years
    Financial aspects
    Comment
    including the technical flood protection
    Others
    Participatory process
    No
    Is it possible to transpose this action in a different context?
    No, it is site specific
    Risk reduction
    Hazard
    +
    Exposure
    +
    Vulnerability
    +
    Feasibility
    Technical Feasibility
    0
    Economic Feasibility
    +
    Environment
    Water
    0
    Soil
    +
    Vegetation
    +
    Landscape
    0
    Biodiversity
    +
    Society
    Quality of Life
    +
    Community involvement
    ?
    Landscape Heritage
    ?
    Economy
    Revitalization
    ?
    Local Economy
    ?
    25000000.00